Capacity Planning View

Monte Carlo forecast for work completion at /work?tab=capacity.

Components

Forecast Card

Summary showing: - Backlog size: Items remaining - P50/P85/P95 dates: Completion estimates at different confidence levels - Throughput stats: Mean ± standard deviation - Warnings: Insufficient history or high variance indicators

Confidence Band Chart

Burndown projection with three bands: - P50 (green): Optimistic - 50% chance - P85 (amber): Target - 85% confidence (recommended for planning) - P95 (red): Conservative - 95% confidence

Throughput Histogram

Distribution of historical throughput with: - Bar chart showing frequency distribution - Vertical line at mean - Shaded ±1σ region

Interpretation

Percentile Use Case
P50 Best-case scenario, internal targets
P85 Recommended for external commitments
P95 High-stakes deadlines, contracts

Warnings

  • Insufficient History: Less than 14 days of data; forecast unreliable
  • High Variance: Standard deviation exceeds mean; consider longer history window

Data Requirements

Requires work_item_metrics_daily with items_completed data. Run:

dev-hops metrics daily --with-work-items