Capacity Planning

Forecast work completion using Monte Carlo simulation on historical throughput data.

Overview

Capacity planning answers the question: "When will we finish N items?" or "How many items can we complete by date X?"

It uses historical throughput variance to simulate many possible futures, providing completion estimates with confidence intervals (50%, 85%, 95%).

Core Concepts

Throughput Distribution

Historical throughput is measured as items_completed per day/week from work_item_metrics_daily. The distribution captures:

  • Mean throughput: Average completion rate
  • Variance: Day-to-day fluctuation
  • Trends: Acceleration or deceleration over time

Monte Carlo Simulation

Rather than a single-point estimate, Monte Carlo simulation runs thousands of scenarios:

  1. Sample from historical throughput distribution
  2. Accumulate completions until target reached
  3. Record the completion date
  4. Repeat 10,000+ times
  5. Calculate percentiles for confidence intervals

Confidence Intervals

Percentile Meaning
P50 50% chance of completing by this date (optimistic)
P85 85% chance - reasonable planning target
P95 95% chance - conservative estimate with buffer

Data Model

Input: Historical Throughput

Source: work_item_metrics_daily

SELECT day, team_id, work_scope_id, items_completed
FROM work_item_metrics_daily
WHERE day >= today() - INTERVAL 90 DAY
ORDER BY day

Input: Backlog

Source: work_items (open items)

SELECT COUNT(*) as backlog_size
FROM work_items
WHERE status NOT IN ('done', 'closed', 'cancelled')
  AND team_id = :team_id

Output: Forecast Record

New table: capacity_forecasts

Column Type Description
forecast_id String Unique identifier
computed_at DateTime When forecast was computed
team_id String Team scope
work_scope_id String Project/board scope
backlog_size Int Items remaining at forecast time
target_items Int Items to complete (if fixed-scope)
target_date Date Target deadline (if fixed-date)
p50_date Date 50th percentile completion date
p85_date Date 85th percentile completion date
p95_date Date 95th percentile completion date
p50_items Int Items completable by target_date (50th)
p85_items Int Items completable by target_date (85th)
p95_items Int Items completable by target_date (95th)
throughput_mean Float Historical mean throughput/day
throughput_stddev Float Historical stddev
simulation_count Int Number of simulations run
history_days Int Days of history used

API

GraphQL Query

type CapacityForecast {
  forecastId: ID!
  computedAt: DateTime!
  teamId: String
  workScopeId: String
  backlogSize: Int!

  # Fixed-scope: "When will we finish N items?"
  targetItems: Int
  p50Date: Date
  p85Date: Date
  p95Date: Date

  # Fixed-date: "How many items by date X?"
  targetDate: Date
  p50Items: Int
  p85Items: Int
  p95Items: Int

  # Throughput stats
  throughputMean: Float!
  throughputStddev: Float!
  historyDays: Int!
}

type Query {
  capacityForecast(
    teamId: String
    workScopeId: String
    targetItems: Int
    targetDate: Date
    historyDays: Int = 90
  ): CapacityForecast

  capacityForecasts(
    teamId: String
    fromDate: Date
    toDate: Date
    limit: Int = 10
  ): [CapacityForecast!]!
}

CLI Command

# Compute forecast for a team
dev-hops forecast capacity \
  --team-id team-123 \
  --target-items 50 \
  --history-days 90 \
  --db "$DATABASE_URI"

# Compute for all teams
dev-hops forecast capacity \
  --all-teams \
  --db "$DATABASE_URI"

Algorithm

Monte Carlo Implementation

def monte_carlo_forecast(
    throughput_history: List[float],  # Daily throughput samples
    target_items: int,
    simulations: int = 10000,
) -> ForecastResult:
    """
    Run Monte Carlo simulation for completion date.

    Returns percentile completion dates (p50, p85, p95).
    """
    completion_days = []

    for _ in range(simulations):
        remaining = target_items
        days = 0

        while remaining > 0:
            # Sample from historical throughput
            daily_throughput = random.choice(throughput_history)
            remaining -= daily_throughput
            days += 1

            # Safety: cap at 365 days
            if days > 365:
                break

        completion_days.append(days)

    return ForecastResult(
        p50_days=np.percentile(completion_days, 50),
        p85_days=np.percentile(completion_days, 85),
        p95_days=np.percentile(completion_days, 95),
    )

Edge Cases

Scenario Handling
Zero throughput days Include in distribution (realistic)
< 14 days history Return warning, use available data
No history Return error, cannot forecast
Extremely high variance Flag in response, suggest longer history

Visualization

Located at /work?tab=capacity in dev-health-web.

Burndown with Confidence Bands

Implemented as ConfidenceBandChart component showing three projection lines:

Items
  ^
50|████████████████████
  |  ████████████████████
  |    ██████████████████████  <- P95 (conservative - red)
  |      ████████████████████████
  |        ██████████████████████████  <- P85 (target - amber)
  |          ████████████████████████████
  |            ██████████████████████████████  <- P50 (optimistic - green)
  +-----------------------------------------> Days
              Today        P50    P85   P95

Throughput Histogram

Implemented as ThroughputHistogram component showing: - Bar chart of throughput distribution (normal approximation) - Vertical line marking the mean - Shaded region for ±1 standard deviation

Forecast Summary Card

ForecastCard component displays: - Backlog size and completion targets - P50/P85/P95 completion dates - Throughput statistics (mean ± stddev) - Warning indicators for: - insufficientHistory: < 14 days of data - highVariance: stddev > mean (unreliable forecast)

Implementation Phases

Phase 1: Core Computation (Backend) ✅

  • Monte Carlo simulation function
  • Throughput history loader
  • Backlog size query
  • ForecastResult dataclass

Phase 2: Storage & Persistence ✅

  • capacity_forecasts table schema
  • ClickHouse sink implementation
  • SQLAlchemy sink implementation

Phase 3: CLI & Jobs ✅

  • forecast capacity CLI command
  • Scheduled job for daily forecast refresh
  • Team/scope iteration

Phase 4: GraphQL API ✅

  • CapacityForecast type
  • capacityForecast query resolver
  • capacityForecasts list query

Phase 5: Frontend UI (dev-health-web) ✅

  • CapacityView component: Main view at /work?tab=capacity
  • ForecastCard: Summary card with P50/P85/P95 dates and warning indicators
  • ConfidenceBandChart: ECharts-based burndown with confidence bands
  • ThroughputHistogram: Distribution chart with mean/stddev overlays
  • GraphQL integration: Uses graphqlClient.query() fetch pattern
  • Sample data: Test mode fallback for Playwright tests

Non-Goals (v1)

  • Story point weighting (use item count only)
  • Sprint/iteration boundaries
  • Resource allocation optimization
  • Individual contributor forecasts
  • Real-time streaming updates

References